Shipping & costs, made clear

From container loading to final delivery, understand the trade term and confirm who handles each stage and cost.

Discuss your projectSteel framing components being loaded for shipping

Common shipping questions

What happens between the factory and the site?

The journey can include factory prefabrication, packing and container loading, export formalities, international freight, import clearance, local transport and on-site assembly. The quotation and contract should name who arranges and pays for each stage.

Who handles customs clearance under FOB?

Under Incoterms® 2020 FOB, the seller handles export clearance where applicable; the buyer handles import clearance. Risk transfers when the goods are on board the buyer-nominated vessel at the named port of shipment.

Does an FOB price cover delivery to my site?

No. FOB delivery occurs on board at the named shipment port. The buyer generally takes on main carriage, import formalities and destination costs after that point. Check the written quote separately for materials, packing, design and installation.

Is FOB right for every container shipment?

Not always. If a container is handed to the carrier at a terminal before loading onto the vessel, ICC notes that FOB may not fit; FCA may be more suitable. Name the exact delivery point and rule version in the contract.

How do DAP and DDP differ?

With DAP, the seller brings the goods to the named destination and bears risk up to that point, while the buyer handles import clearance and duties. DDP also puts import clearance and applicable duties on the seller; local rules may limit its practicality.

Which costs should I check line by line?

Check building components and materials, design and engineering, packing, port fees, freight and insurance, import taxes, local transport, lifting, foundations and on-site installation. Each line should say included or additional.

Does factory production time equal delivery time?

No. Design sign-off, factory production, international shipping, import clearance, local approvals and site assembly are separate stages. Ask for a timeline broken down by stage, with room for freight and site conditions.